Noble Street Bridge Project
This project is overseen by Jefferson County Highway Department & Stantec Consulting Services.
Phase 1 Construction ( 2024-2025)
Construction is expected to go out to bid by the end of April 2024 and the underground and overhead utility work will begin Summer of 2024. National Grid and Village utilities will have to be relocated.
The Village Department of Public Works will be turning off water to residents affected due to the relocation of water lines. The Village Office will notify residents that will be affected via village website, Facebook page and 7 News.
Phase 2 Construction (2025)